
Battledown Flyover
Worting Junction
The topics of Worting
Junction and the Battledown Flyover can be approached together. First, a brief
recap of the situation so far. The ''London & Southampton Railway Company'' had
been incorporated on 25th July 1834 to construct a 77-mile line between its
namesakes. Building work was arranged to commence at both ends of the line, thus
two sections of track would eventually meet in the middle to complete the
through route between the capital and Hampshire. Train services commenced
between Nine Elms (then the company's London terminus) and Woking Common on 21st
May 1838, and this was followed on 24th September of the same year by the
commissioning of a westward extension to Winchfield & Hartley Row. On 10th June
1839, through running between London and Basingstoke began, whilst on the same
day, services commenced between Winchester and Southampton on the western
portion of the route. Finally, continuous-running between Nine Elms and
Southampton was possible from 11th May 1840.
In 1844, the LSWR (as the company had been known since 1839) had set its sights
on invading the West Country, with branches stretching out as far as Exeter,
Plymouth, and Penzance. In this year, powers were obtained for a branch line
from Bishopstoke (Eastleigh) to Salisbury, which would make a trailing
connection with the main line at the former. This arrangement meant that trains
from London would not have direct access to the line, but the LSWR Board was not
fazed: a more direct route to the cathedral city was already in the pipeline.
Plans had been devised to create a cut-off line between Winchester and
Salisbury, now that a line to Exeter was very much on the agenda. In 1846, Royal
Assent was granted for the ''Whitchurch Cut-Off'', the plans of which had been
revised in order to have the line leave the Southampton trunk route at Worting,
three miles south west of Basingstoke, rather than at Winchester. The Salisbury
branch opened to goods traffic on 27th January 1847, and for passengers on 1st
March of the same year. The Cut-Off line was over ten years away from
completion: work had started, but was later abandoned as a result of a financial
crisis. Construction resumed in the early 1850s, and the route eventually opened
in two stages:
Worting to Andover: 3rd July 1854
Andover to Salisbury: 1st May 1857
Worting Junction was born. The Salisbury line was single-track throughout, and
construction of an extension to Yeovil, and ultimately Exeter, soon began. The
''Salisbury & Yeovil Railway Company'' had been incorporated on 3rd July 1854 to
proceed with the first stage of the route. The independent concern initially
floundered as a result of money trouble, but construction formally began on 3rd
April 1856, with the cutting of the first sod at Gillingham (Dorset). The route
was opened in three stages:
Salisbury to Gillingham: 1st May 1859
Gillingham to Sherborne: 7th May 1860
Sherborne to Yeovil: 1st June 1860
As per the section between Worting Junction and Salisbury, the line was
single-track throughout, and the LSWR had already pressed ahead with the Exeter
extension. In fact, so advanced was the latter that through running between
Waterloo and Exeter (Queen Street) was possible from 19th July 1860 (Waterloo
had superseded Nine Elms as the LSWR's London terminus on 13th July 1848). The
line was profitable at an early stage, and double-track working along the entire
route from Worting Junction to Exeter commenced in July 1870.
From the outset, a flat junction was provided at Worting, which saw Southampton
and Salisbury routes converge on the level. Naturally, this caused conflicting
movements, for trains from the alternate routes had to cross each other's paths,
a situation which became more problematic as traffic increased. Nearing the end
of the 19th Century, the LSWR sought to resolve this bottleneck: within an Act
dated 6th July 1895, powers were obtained for widening on the north side of the
route between Basingstoke and Worting Junction. This three-mile-long section was
to be quadrupled to provide dedicated pairs of tracks for the two routes, and a
''flying junction'' installed to eliminate conflicting movements. Of the four
lines, the central tracks were to form the approaches of the Salisbury route,
whilst the outer tracks would be for Southampton traffic. The new ''up'' line
from Southampton was raised upon an embankment and carried over the double-track
from Salisbury upon a lattice girder bridge. The latter was of roughly
semi-circular cross-section, comprising a pair of partially staggered lattice
girder sides of 145-feet length. A brick-built signal-box, similar in design to
that which still exists at Yeovil Junction, emerged on the ''up'' side of the
junction, north of the flyover. In the earliest years, the signalman had been
housed in a hut beside the line, and would step over the tracks to pull the
levers to change the points. This latterly led to the recommendation of having
all leavers on one side of the running lines, to save the signalman the trouble
of hopping over tracks to switch the direction of travel. Battledown Flyover was
brought into use for regular traffic on 30th May 1897.
The Bournemouth electrification, approved in September 1964, sought to extend
third rail from Brookwood, Surrey, to Branksome, Dorset (just west of
Bournemouth), and replace the existing mechanical semaphore signalling with
colour lights controlled from new panel boxes. This scheme replaced an earlier
proposal to electrify as far as Weymouth on the Southampton trunk line, and to
Salisbury on the West of England Main Line, using a system of overhead wires. At
Worting Junction, the lines were re-laid using continuously welded rail clipped
to concrete sleepers, and a substation housing a 2-MegaWatt rectifier installed
at the site. Control of the junction then passed to a new panel at Basingstoke
on 20th November 1966, coinciding with the commissioning of colour aspect lights
and the abolition of the mechanical signal box.
2nd July 1966

This atmospheric shot depicts Merchant Navy Class No. 35008 ''Orient Line'' ascending the single-track incline
towards Battledown Flyover. The SR head code is that of Bournemouth to Waterloo. © David Glasspool Collection
26th June 2002

Battledown Flyover is viewed from the Salisbury direction, as an excursion fronted by Merchant Navy Class
No. 35005 ''Canadian Pacific'' glides under the bridge span, returning to Waterloo from Bristol Temple Meads.
David Glasspool
24th April 2009

Class 159 No. 159015 is seen diving under Battledown Flyover, Exeter-bound. The bridge span has been repainted
since the previous photograph taken in 2002. © David Glasspool Collection
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated