
Lewisham
The year is 1843 and
the South Eastern Railway has completed the construction of its Reigate Junction
(Redhill) to Dover trunk line. Boasting an unrivalled link between the capital
and the Kent Coast (there being no LC&DR in existence), the company deems it
appropriate to begin developing its suburban network. The necessary impetus for
this is given by the August 1844 agreement between the concern and the London &
Greenwich Railway, which saw the former take out a 999 year lease on the
latter’s metals. These extended from the capital’s first terminus, London
Bridge, across an 878-arch viaduct to Deptford, then over Deptford creek into
Greenwich. The SER would have preferred this line to form the beginnings of its
own suburban route across North Kent (ultimately to Strood), but unfortunately
for the company, the Royal Observatory had other ideas. Astronomy very much
taking precedence over the then new form of transport, the railway was viewed as
an ‘’interference’’ risk to the study of the skies. Thus, if the SER wanted to
pursue its suburban ambitions, a new south-easterly entrance to the capital was
required. In 1846, Parliament formally authorised modified plans presented by
the SER; these still outlined a route laid roughly parallel with the Thames,
passing through Charlton and Woolwich. However, of significance was the
southward diversion of the line’s westerly end through Lewisham, which added a
further 1½ miles onto the distance between London Bridge and Charlton, and
required the boring of a 1681 yard long tunnel to the east of Blackheath.
On 30th July 1849, the SER opened the North Kent Line through Lewisham,
Blackheath, and Woolwich, it subsequently continuing onto Dartford, Gravesend,
and Strood. A station came into use at Lewisham from the outset, but unlike the
site of today, the layout was merely a two-platform affair, being of no more
importance or significance than nearby Blackheath. Indeed, this situation was to
alter on the advent of the ‘’Mid-Kent Railway’’, the concern of which had been
formed to forge a line to Beckenham. This was planned to spur off the SER’s
suburban route at Lewisham, and be further extended to Addiscombe. On 1st
January 1857, the double-track Mid-Kent Line came into use throughout to
Beckenham, with Addiscombe being reached some seven years later. For this, the
SER undertook a comprehensive rebuilding programme at Lewisham. This provided
the station with four platform faces: the two existing surfaces served the North
Kent Line, whilst a pair of additional platforms were installed for the Mid-Kent
Line. The station laid immediately east of the diverging routes, which provided
the SER with the opportunity to construct the main station building within the
triangular apex created by the junction. Indeed, it was the subsequent decade
which witnessed the railway company fabricating stations on the cheap (those on
the 1866-opened Dartford Loop Line once serving as fine examples), thus Lewisham
escaped with a permanent-looking structure, a type synonymous with the original
route of 1849. The building was constructed using the now familiar yellow brick
of the SER, complete with stone lining (as per Gravesend, Dartford, and Erith
stations, to name but a few), five pitched roof sections, and a 68-foot façade.
Interestingly, however, the main building was designed with just a
single-storey, a feature which would seem to derive from the fact that the
structure is triangular in nature. Copious rectangular canopies were provided on
all platforms, these demonstrating the once common – and pleasing – SER valance
design, this of which can still be seen in use at Blackheath. A clapboard
platform structure was not absent, however, and such appeared on the ‘’up’’
Beckenham line platform, demonstrating an almost identical appearance to that
which formerly resided on the ‘’up’’ side at Bexley. This suggests that it was
perhaps a belated addition to the station. Finally, to the west of the
platforms, sitting on the ‘’up’’ side next to the diverging lines, was a signal
box of SER design. Two-storeys high, it was of typical clapboard construction,
featuring a pitched roof and sash-style windows. It came into use approximately
two decades after the Mid-Kent Line.
Platform Canopy Lengths (south to north)
Platform 1: 60 Foot
Platform 2: 130 Foot
Platform 3: 135 Foot
Platform 4: 60 Foot
Façade Canopy: 68 Foot
The SER’s woes caused by the Royal Observatory preventing an extension of the original Greenwich line may have been forgiven, for in 1852, the latter began using the railway company’s telegraph system to transmit Greenwich Mean Time. The transmission was centred on Lewisham station, which subsequently dispersed the signal to all other sites on the railway network. Those stations on a latitude which was the same as, or east of, Dover, were five minutes fast of Greenwich Mean Time. Going westwards to Winchester, Hampshire, times were five minutes slow, and by the time Truro in Cornwall was reached, the time was twenty minutes behind that of Greenwich. Transmission of the signal commenced on 2nd November, and eventually, clocks nationwide became synchronized on the same time.
Since the inception of the Mid-Kent Line, the station had been adorned with the name ‘’Lewisham Junction’’. An important interchange point between this route and the North Kent Line (the former having been extended to Hayes on 25th May 1882), the station has never been host to its own goods yard as such. However, some 450 yards to the east of the North Kent Line platforms did reside an interesting arrangement, which was once a common feature during the early railway age. Trailing off the ‘’down’’ line, in a westward direction, was a single siding, some 125 yards in length. Dedicated to goods traffic, this assumption is confirmed by the line’s termination at a diminutive wagon turntable (a familiar sight when both horse and human shunting of wagons was prevalent). This in turn fed two spurs, each 30 yards in length; the first of these continued parallel with the running lines for the whole of its extent, whilst the second skewed off at nearly ninety degrees. Of course, goods traffic for the SER’s inner London suburban network was amply handled at Bricklayers Arms, and indeed, proposals to expand the freight yard here emerged concurrent with the plans outlining a new engine shed on the Crayford Marshes (‘’Slades Green’’, as it would become known), in 1897.
March 1981

BR-designed 4 EPB No. 5347 trundles in with a semi-fast Charing Cross service from Gillingham, via Woolwich.
© David Glasspool Collection
15th March 1990

Bulleid-designed 4 EPB No. 5155 is depicted alongside those platforms which serve trains from the Hayes line,
Dartford via Sidcup, and the main line through Orpington. The canopy valance here is a mixture of timber and
riveted steel. © David Glasspool Collection
27th January 2007

The main building was completed in 1856, in preparation for the commencement of Mid-Kent Line services on
1st January of the following year. Typical SER features include the arched window frames, yellow brickwork,
and stone lining. The canopy has indeed been simplified; formerly, a valance identical to that still in evidence
at Blackheath was present. © David Glasspool Collection
Next: the History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated