
London Charing Cross
Change came early on
in Charing Cross’ existence, initially for the better. Under SER ownership, the
terminus was a hub for Dover boat traffic, this naturally affecting receipts in
the hotel. Thus, in 1878, the original 250 rooms were increased by a further
ninety with the opening of an extension on the opposite side of Villiers Street,
on the station’s north eastern elevation. The extension was linked to the main
hotel, the latter designed by E.M. Barry, by an ornate enclosed footbridge. This
was followed in 1887 by the widening of Hungerford Bridge by nearly 50 foot,
which increased its track capacity from four to seven lines. Consequently, this
saw the original Saxby & Farmer signal box taken out of use and a new one,
similarly suspended across the tracks in the same location, brought into use in
February 1888. Furthermore, platforms 1 and 2 could now be lengthened and skewed
to accept the longer train formations. Opening with the then newly quadrupled
section of track between Metropolitan Junction and Hungerford Bridge on 2nd June
1901 was a 54 foot turntable. Located on the South Bank, on the ‘’up’’ side of
the Hungerford Bridge approaches, it was known as ‘’Belvedere Road’’ and used by
those terminating engines from Charing Cross. However, at least to the general
passer-by, the most significant change to the station in its earlier years was
the replacement of the trainshed roof. On 5th December 1905, a weak tie rod
connection failed at the river end of the trainshed, workers subsequently
scrambling to safety to avoid any falling components. The effect of this took a
number of minutes to transpire, but when it did, a progressive collapsing
sequence from the Thames end of the structure ensued, which saw 70 foot of the
510 foot long structure fall to the ground, taking the upper layers of the
supporting walls with it. Five deaths were resultants of this accident and
although most of the trainshed remained intact, the SE&CR (as it had been from
1899) dismantled the remnants and installed a much more solid - although less
imposing - ridge-and-furrow roof on partially rebuilt walls. The station was
closed during this time, which in itself was convenient, for it allowed time for
engineers to examine the strength worthiness of the railway bridge. By the turn
of the century, heavier locomotives were being introduced, which became
unsuitable for the comparatively weak structure of Hungerford Bridge. Initially,
only a small number of additional girders were put in place, but this was far
from adequate. After the station re-opened on 19th March 1906, restrictions were
imposed which barred the larger locomotive classes from Hungerford Bridge and
also saw that no more than two tracks upon the structure were under use
simultaneously. It was not until 2nd August 1917 that the SE&CR finally secured
Parliamentary approval for the strengthening of the bridge, having tried
unsuccessfully in the previous year, but even then no major work was carried
out.
Meanwhile, political trouble had been brewing. Charing Cross had two significant
factors riding against it: 1) it was positioned at a strategically important
location, this being considered the heart of London, where all external
distances were measured from; 2) Hungerford Bridge was looked upon as a huge
eyesore on the landscape, support having gradually been rallied over the years
for its demolition. In particular, certain figures within the 1889-formed London
County Council favoured the demolition of both the railway bridge and station:
the former would be replaced by a road bridge, the latter would be superseded by
a new terminus on the South Bank. After a consultation in 1901, the SE&CR were
reluctant to push through such a scheme, although it would be the LCC which
would have to provide the finance for a new terminus, as compensation for the
move. It had only been in the previous year that the railway company had secured
Royal Assent for the expansion of Charing Cross on both sides, which included
the Hungerford Bridge, but unrest on the side of the LCC had seemingly delayed
these proposals. With agreement between the SE&CR and LCC not being reached, the
scheme was not pursued – for now.
The advent of the Southern Railway in 1923 heralded modernisation at the
terminus. Fairly swiftly, the company began implementing signalling alterations,
the first casualty being the 1888-installed signal box. This went out of use in
August 1924 and for nearly two years thereafter, the layout was worked by a
temporary signal box positioned within the apex of the diverging lines of
platforms 2 and 3. During this time, four-aspect colour lights were put in
place, the now obsolete 1888 signal box was demolished, and the signal cabin at
nearby Waterloo Junction was dismantled and re-erected on the Isle of Wight, at
Ryde St Johns Road. However, before the colour light system had been brought
into use, yet another significant development was made. The ex-SE&CR’s suburban
lines fell into the SR’s earliest electrification proposals with the ex-LSWR’s
third rail system. Electric working from Holborn Viaduct and Victoria, to
Orpington commenced as early as 12th July 1925, and this was then extended from
the latter, up to Charing Cross on 28th February of the following year. The
scheduled electric timetable came into force on the North Kent Lines on 6th June
1926, which at least solved one problem: bridge strength. Now that train weight
was equally distributed among the carriages of EMUs, the operating restrictions
of Hungerford Bridge could be overcome, strengthening work now not being
essential. Colour light operation was brought into use on 27th June 1926; this
included the commissioning of a new 90 foot long signal box, again straddled
across the tracks in the same position as those cabins which preceded it. It was
of simple all-timber construction, again reducing potential weight, and
comprised 100 miniature power levers. Boat traffic had since been transferred to
Victoria in 1920.
19th June 1976

Approaching the terminus on the service from Dover, we see that a rolling stock siding once existed across
Hungerford Bridge. On this occasion, it was packed to the gunwales with EPB Rail Blue suburban stock. On
the right, Bulleid-designed EPB stock is in evidence. In the background can just be seen Charing Cross signal
box, straddling the tracks. It had closed on 16th April of that year. © David Glasspool Collection
19th June 1976

The Charing Cross approaches are again seen from an un-refurbished 4 CEP, this time working the 11:00
service to Dover. A BR-designed 2 EPB, in Rail Blue livery, is seen trailing another train as it heads into the
terminus. © David Glasspool Collection
29th October 1983

Engineers' crane DRS 81334 is in attendance whilst repairs to the bridge deck are undertaken below platform 2.
The work has required removal of the running rails and their supporting timber baulks, which have been placed
on the far end of platform 2 and between the rails of platform three, whilst the third rail has simply been propped
up clear of the bridge deck. Although suburban side platforms 1 to 3 are closed, platforms 4 to 6 remained open
and passengers are joining a mainline service headed by a 4 VEP in platform 4. In the distance a 4 EPB may be
seen stabled in the carriage siding at the far end of the bridge. This unit will remain trapped in the siding until
such time as the engineers' possession has been given up later on Sunday evening. © David Morgan
<< Previous Next: the History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated