
Paddock Wood
Today, this remains
as a large and spacious layout, testament to the SER’s far-sightedness of the
need for fast trains to overtake stopping services. This same principle was
borne in mind during the development of stations at Tonbridge, Ashford, and
Canterbury. ‘’Maidstone Road’’ station, as it was initially named, came into use
with the SER’s Tonbridge to Ashford extension on 1st December 1842. It was
located within the Parish of Brenchley and resided 45½-miles from London and,
when the final push to the coast was completed in February 1844, 41¼-miles from
Dover. Two main platform surfaces were separated by a quadruple-track
arrangement, an impressive affair given that the site was in decidedly rural,
sparsely populated surroundings. Indeed, the raison d’être of the station
appears purely as an interchange point on the main line for Maidstone traffic,
the town of which resided ten miles distant to the north. By this stage, plans
were already well advanced for the building of a single-track branch to the
county town, replacing a horse-drawn coach service between there and the
railway. The latter ran six times daily in each direction. It was reported in
the SER’s records that 21,790 passengers used Maidstone Road between 1st
December 1842 and 28th February 1843.
The Maidstone branch, proposed to be 10-miles 2-chains in length, was authorised
on 27th June 1843. The Bill allowed the SER to raise a capital of £112,000
(£9,360,000 at 2008 prices) for the line’s construction, with the option of
taking out loans amounting to an additional £37,300 (£3,120,000 at 2008 prices).
Construction took little over a year, the route being inspected by the Board of
Trade on 23rd September 1844, two days before opening. The completed line was
marginally shorter than originally proposed, extending for 9-miles 65-chains.
Resident Engineer was George Robert Stephenson, nephew of George Stephenson of
‘’Rocket’’ fame. The single-track Maidstone branch was characterised by shallow
gradients and easy earthworks, and the line followed the valley of the River
Medway for its entirety. Indeed, the original Bill stipulated that the steepest
gradient on the line be no more than 20-feet in the mile, and the tightest curve
to have a radius of 1320-feet upwards. It was noted at the time that sufficient
land had already been purchased for the laying of a second track, west of the
existing rails. Should the route later be doubled, bridges and viaducts under
the line would require widening, said at the time to be ‘’a very simple
process’’. Major General Pasley was the inspecting officer, and he was
accompanied during his visit by Captain Coddington, engineer Stephenson, and Mr
Benjamin Cubitt. Sleepers were fabricated from Baltic timber and the line was
reported to be well ballasted, drained, and properly fenced. The branch line was
recommended for opening on 25th of the same month, as had originally been
proposed by the SER.
The main line station had been known unofficially by passengers as ‘’Paddock
Wood’’ since opening, taking its name from the woodland carved open to
accommodate the railway. The station formally assumed this name when the branch
to Maidstone was commissioned. Paddock Wood, like Tonbridge and Ashford, avoided
the SER’s economical approach to station provision, and brick, rather than
clapboard, was used for the main structures. The Italianate style was the order
of the day, and a splendid red-brick main building of this design appeared on
the ‘’down’’ platform. It was two-storeys high, was frescoed at its edges with
stone, and was essentially an enlarged version of those Italianate main
buildings commissioned along the Hastings line. The ‘’up’’ platform comprised
structures fairly modest in comparison: a two-storey-high red-brick clock tower,
virtually identical to that which the SER commissioned at Tunbridge Wells, sat
in the company of a single-storey brick building with a hipped slated roof. The
latter was flanked either side by timber waiting shelters, which provided the
only protection from the elements – indeed, neither platform surface was host to
a proper canopy. The clock tower appears to have been incorporated purely to
form the southern abutment of the footbridge erected to span all four tracks.
The latter was of lattice construction, was roofed, and entered the upper floor
of the ‘’down’’ side building.
Goods facilities at the first station were concentrated at the western end of
the layout, sandwiched in-between the road bridge and platform ends. The
platform loops both featured small wagon turntables,
installed in a straight line north to south, to link a westward-facing siding
on the ‘’up’’ side with a perpendicular-built goods shed on the ‘’down’’ side.
Thus, this link track cut across all four tracks at right angles, but the
through lines did not feature wagon turntables. Further, lengthy sidings appeared at the eastern end of the station, around the
time of the Maidstone branch’s doubling in spring 1846. Indeed, the advent of
the branch had seen the commissioning of an eastward-facing bay platform on the
‘’down’’ side, which allowed trains not continuing onto Tonbridge to leave the
‘’down’’ loop clear. The layout was controlled by a pair of SER-designed
clapboard signals boxes, situated either side of the station. The first was
positioned at the western end of the layout, suspended above a siding fed by the
‘’down’’ loop, upon a series of wooden struts. The cabin, which featured
trademark SER sash-style windows, became ‘’Paddock Wood West Yard Signals’’, and
its elevated position allowed the signalman a clear view over the road bridge to
the west and the lattice footbridge to the east. The second signal box, to the
east, was suspended upon a brick base above a siding which fed off the ‘’up’’
platform loop. Again, its height afforded an unhindered view over the station
footbridge. The cabins originally had signal arms sprouting from their roofs,
but these were removed during a later re-signalling in 1898.
The passing of the ‘’Maidstone & Strood Act’’ on 4th August 1853 allowed the SER
to make a northward extension of its branch line. The Maidstone branch thus
became a complete loop on the opening of this double-track section, which linked
the county town and, indeed, the Weald of Kent main line, with the 1849-opened
North Kent Line. The cost of the extension had been estimated at £340,000
(£24,500,000 at 2008 prices), the sum of which would be met by the issue of
shares. The SER was also authorised to borrow a further £146,600 (£10,500,000 at
2008 prices). Of direct relevance to Paddock Wood station was the forming of the
‘’Cranbrook & Paddock Wood Railway’’ on 2nd August 1877, the full details of
which can be found within the Hawkhurst section. Fundraising for this scheme was
painfully slow, and the first section of the branch line, between Paddock Wood
and Hope Mill (Goudhurst), did not open until 1st October 1892. Passenger
services reached Hawkhurst, 11½-miles from the main line, on 4th September of
the following year. In contrast to the SER’s Maidstone branch, the single-track
line featured steep gradients and tight curves. A dedicated eastward-facing
‘’up’’ side bay line was brought into use at the main line station for the
branch.
Coinciding with the opening of the branch line to Hawkhurst in 1893 was a
rebuild of Paddock Wood station. All existing structures on the ‘’up’’ platform
were obliterated, and the existing footbridge was also taken down. On both
platform surfaces, proper canopies were erected. Each were 300-feet in length
and covered the extent of the bay platform faces. The canopies were of
semi-circular cross-section and sported the SER’s trademark clover-patterned
valance. A new single-storey red-brick station building, with hipped slated
roof, came into use on the ‘’up’’ side, its appearance, albeit somewhat plainer,
being akin to the existing main structures at Ashford. To its immediate west, it
was joined by a flat-roof timber waiting shelter. A new lattice footbridge,
again roofed, came into use, and emerged through the middle of the canopies. As
part of the same works, the wagon turntables and connection with the
perpendicular goods shed at the western end of the layout were abolished; the
number of sidings on the ‘’up’’ side here were, however, increased. The large
‘’down’’ side Italianate station building was retained, and this was joined by a
collection of clapboard huts to its west.
18th May 1961

A westward view from the lattice footbridge reveals ''H'' Class No. 31305 entering the ''down'' loop with the
9:42 AM service to Maidstone West, three gleaming Bulleid vehicles in tow. On the right is the then new
electrical control room, flanked by BR(S) concrete bracket lampposts. Just in front of the locomotive, we
are afforded a glimpse of the prefabricated concrete extension, which has yet to have its run-in name board
affixed (this of which can be seen resting on the floor). On the right again, but this time in the background,
is visible the goods shed, clearly at right angles to the running lines. This, although still in railway use at the
time, had for long lacked a rail connection. Further sidings existed behind the canopy on the left, the connection
with these being visible beyond the semaphores. © David Glasspool Collection
22nd May 1961

The end is nigh as ''H'' Class No. 31543 is seen in the ''up'' bay at Paddock Wood, fronting a Hawkhurst train.
The clover-patterned SER canopy valances are seen to good effect here; the ''down'' side Italianate main
building and lattice footbridge are hidden by the locomotive. © David Glasspool Collection
6th November 2004

An Ashford-bound view shows the remaining ''up'' building of 1893,which has retained the majority of its canopy,
minus much of the ornate valance. The glazed shelter on the left replaced an earlier CLASP structure in about 1988,
and this in turn had superseded the SER Italianate building. David Glasspool
Next: The History Continues >>
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated