
Shortlands Junction
The railways in the
area have a very complicated history, several independent concerns having been
formed to build sections of what eventually became constituents of the
‘’Chatham’’ main line. Rails have been in the vicinity since 1858, when the ''West
End of London & Crystal Palace Railway'' (WEL&CPR) commissioned a double-track
line between Norwood (Junction) and Shortlands (then known as ‘’Bromley’’). This
formed the final section of the company’s line from Battersea, and powers for
the extension had been obtained in 1854. The WEL&CPR came into use piecemeal:
Crystal Palace to Wandsworth Common: 1st December 1856
Crystal Palace to Norwood (Junction): 1st October 1857
Wandsworth Common to Pimlico Terminus (Battersea): 29th March 1858
Norwood (Junction) to Bromley (Shortlands): 3rd May 1858
Another independent company known as the ‘’Mid-Kent Railway’’ commissioned an
extension of WEL&CPR metals between Shortlands and Southborough Road (Bickley).
This came into use on 5th July 1858 and was leased by the SER from the outset,
as a continuation of the route from Lewisham. By this time, the ‘’East Kent
Railway’’ (EKR) had advanced on its approach to the capital, and in the
following year it connected with the Mid-Kent Company at Southborough Road, by
means of its ‘’Western Extension’’ from Strood. The EKR was known as the
‘’London Chatham & Dover Railway’’ from 1st August 1859. From 3rd December 1860,
the company commenced through running between Victoria and Canterbury, taking
over the lease of the Mid-Kent Railway from the SER. Between Shortlands and
Grosvenor Bridge, the LC&DR ran over the metals of the WEL&CPR.
Advent of the Junction
The WEL&CPR had previously been absorbed by the LB&SCR on 1st July 1859, and as
a consequence, the LC&DR was subject to the tolls of its Victoria terminus
rival. This situation eventually came to an end in 1863 when, on 1st July of
that year, the latter completed an avoiding line between Beckenham and Stewarts
Lane, via Herne Hill. The original WEL&CPR became little more than a local
traffic line, the LB&SCR itself having commissioned a cut-off route between
Balham and East Croydon on 1st December 1862.
The need for a relief line was brought to the fore by the LC&DR in 1884. The
company began lobbying Parliament for powers to commence work on an alternative
route to its existing trunk line between Shortlands and Brixton, via Penge. The
company proposed a double-track affair, 4.7 miles in length, spurring off the
existing Crystal Palace and Blackheath Hill (later Greenwich Park) branches at Nunhead, subsequently
re-joining the trunk route at a flat junction to the north-west of Shortlands
station. Royal Assent was finally acquired in 1889, resulting in the formation
of the nominally independent ''Shortlands & Nunhead Railway Company'' on 12th
August of the same year. Building works were completed in 1892, scheduled
passenger services commencing on 1st July of that year. Dubbed the ‘’Catford
Loop’’ from the outset, the diversionary route allowed an additional twenty-one
trains to be run between Bromley, Bickley, and the City. Coinciding with these
improvements was the acceleration of trains on both Crystal Palace and Greenwich
Park branches by between five and six minutes. The Catford Loop was leased by
the LC&DR until 1896, when it absorbed the independent Shortlands & Nunhead
Company.
Early Expansion
Concurrent with the commissioning of the Catford Loop, the LC&DR had already set
its sights on quadrupling the Shortlands Junction to Bickley section of the main
line. The works were extensive, and included comprehensive rebuilds of the
original stations at Shortlands, Bromley LCDR, and Bickley, involving the
provision of four platform faces at each site, arranged in the form of two
islands. The widening covered a route mileage of 2¼ and crucially, expresses
were now able to overtake stopping services. Hitherto, Catford Loop trains had
blocked the running lines when stabled at the original Shortlands layout, where
just two platform faces were available. Signalling of the new arrangement was
carried out by the LC&DR’s favoured contractor, Saxby & Farmer, and two
attractive cabins, built to a standardised design, appeared at Shortlands. The
first was positioned at the ''Chatham'' end of the layout, on the ‘’up’’ side,
perched upon the edge of the embankment; the second cabin was erected about 330
yards to the north west of the station, on the ‘’down’’ side of the tracks,
immediately before the junction of the diverging Catford and Penge routes.
Quadruple-line working formally commenced on 1st May 1894, and tracks were
paired by direction.
Suburban Electrification
Electrification of the inner suburban lines was proposed by the SE&CR in 1921
and was to be started when finance was available. The company was superseded by
the Southern Railway in 1923, and the latter swiftly implemented LSWR-inspired
third rail on these routes. Work began in 1924, the first routes to be affected
including:
London Victoria to Orpington: Via Herne Hill, Shortlands, and Bickley and Orpington Junctions
Holborn Viaduct to Herne Hill
Catford Loop: Loughborough Junction to Shortlands Junction, including the Crystal Palace (High Level) branch.
Alterations at
Shortlands included the erection of a three-storey-high electric substation
within the fork of the junction. It was reported in November 1924 that the steel
framework of this structure had been completed and that erection of the red
brickwork had commenced. The substation housed a trio of 1,500kW rotary
converters, which were ultimately fed current from the Deptford Power House of
the London Electric Supply Corporation, via the SR’s huge electric substation at
Lewisham. Electric multiple units on staff training runs from St Pauls (renamed
‘’Blackfriars’’ in 1937) reached Shortlands on 8th June 1925. Scheduled electric
suburban services from Victoria and Holborn Viaduct, to Orpington, commenced on
12th July of that year.
During 1925, signalling alterations were also enacted at Shortlands. These
included the abolition of the station’s signal box, at the ''Chatham'' end of the
layout, on 20th December. The Saxby & Farmer cabin beside the junction remained,
and its 53-lever frame controlled a slightly revised arrangement which enabled
the termination of Catford Loop services in the ‘’down’’ local platform (No. 4).
Kent Coast Electrification
Formally approved in February 1956, Phase 1 of the Kent Coast Electrification
aimed to ease speed limits at the junction, provide an additional track on the
‘’up’’ side of the diverging routes, and completely modernise the signalling.
Alterations here required the rebuilding of those bridges at the London end of
the station, as the track level was raised, and also involved the construction
of a new ‘power box’’ within the fork of the junction. Re-signalling saw that
the tracks of the quadruple-line section were now paired by use, whereby
adjacent tracks now carried trains in alternate directions. This, combined with
the addition of a single-track on the ‘’up’’ side of the layout, ensured that
services travelling via Penge East could completely bypass the junction,
avoiding conflicting movements with Catford Loop trains. Speed limits at
Shortlands Junction increased from 40 MPH to 60 MPH for the main line, and
trains using the Catford Loop connection were subject to a limit of 40 MPH.
Construction of the ‘’power box’’ was completed by July 1958, and this was
equipped with a push-button route setting panel. Colour light signalling between
Beckenham Junction and Swanley, and Bellingham and Shortlands Junction, came
into use on 31st May 1959, two weeks before the end of scheduled steam on the
‘’Chatham’’ main line. To the east, the range of Shortlands Junction ‘’power
box’’ extended to Bromley South (inclusive). The full accelerated electric
timetable on the route came into effect on 15th June 1959.
Victoria Panel & Chunnel Alterations
On 16th March 1980, the Victoria Signalling Centre came into use at Clapham
Junction. This led to the redundancy of numerous individual signal boxes, and
over subsequent years the panel’s scope was increased. On 20th June 1982, the
panel took over the functions of the ‘’power box’’ at Shortlands Junction, and
on 12th June of the following year, the scope of the signalling centre was
extended to meet the boundary of Rochester’s ‘’power box’’. At this time,
Chislehurst Junction signal box ceased to control the ‘’Chatham’’ main line, but
remained operational for the Tonbridge Cut-Off route. Shortlands Junction
‘’power box’’ was taken over by the permanent way department.
Arguably, the most radical changes at Shortlands Junction since the quadrupling
of 1894 were those undertaken in connection with the opening of ‘’Section 1’’ of
the CTRL. On 1st June 2000, Railtrack applied to the Department of the
Environment, Transport, and the Regions (DETR), for authorisation to construct a
grade-separated junction at Shortlands. Railtrack claimed that the work was
essential to ensure that punctuality and reliability of commuter services was
not adversely affected when an accelerated Eurostar timetable came into use in
September 2003. The planning application specified the acquisition of further
lands to accommodate an enlarged layout, and the retention of both substation
and signal box structures. The plans met formal approval on 22nd June 2001.
Earthworks were substantial. The project involved retaining a double-track flat
junction between the Catford Loop and the slow lines, but would also see the
creation of a completely new double-track underpass between the Catford Loop and
the fast lines. The reasoning behind this was to eliminate conflicts of
movements between Catford Loop traffic using the fast lines and those services
travelling via Penge East. On a par with the works of the Kent Coast
Electrification, a single avoiding track on the ‘’up’’ side was to be retained
as part of the new layout, to allow main line traffic to completely bypass the
junction. The new connection with the Catford Loop was taken under the departing
Penge East route through a 70-metre-long (76½-yards) reinforced concrete box,
producing a descending gradient in the Catford direction of 1 in 50. By April
2002, the majority of earthworks and tunnel construction had been completed, and
the laying of about a mile’s worth of new track ensued. The works were completed
in June 2003, and Eurostar services began running via Fawkham Junction, to reach
the CTRL’s ‘’Section 1’’, on 28th September of that year. Design and
construction of the new arrangement had been subcontracted to civil engineering
firm ‘’Osborne’’, at a cost of £15.5 million.
Shortlands Junction: 1930
Track plan of pre-Kent Coast Electrification layout. Click the above image for a full-size version.
Drawn by David Glasspool
August 1958

Change is imminent as a filthy West Country Class rounds the curve at Shortlands Junction with a Dover Marine
to Victoria boat train, via Penge. In tow are a pair of baggage vehicles and a Blood and Custard Maunsell coach,
the latter sandwiched in-between a pair of green Bulleid-designed carriages. In the distance can be seen the Saxby
& Farmer signal box of 1894 origin, complete with pyramid-shaped roof. On the left, in the foreground, is the
replacement ''power box'', yet to be commissioned and situated behind a still operational ''home'' semaphore
signal. © David Glasspool Collection
Shortlands Junction: 2003
Track plan after Railtrack alterations for Chunnel passenger services. Click the above image for a full-size
version. Drawn by David Glasspool
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool