Gravesend Central
1st December 2013
1st December 2013 was scheduled to be the day of the lattice footbridge's removal. By 13:00, when the above was taken, the main span had already been lifted out and transported off site. © David Glasspool
1st December 2013
A large gap in the canopy makes the former position of the footbridge obvious. The staircases on both sides were still evident.© David Glasspool
22nd December 2013
On 22nd December work was underway lifting the track serving platform 1, to allow realignment in connection with this surface's eastward extension. The ''up'' through line, which the line of wagons can be seen upon in the above view, was due for permanent abolition. A ''Freightliner'' Class 66 was on site this day. © David Glasspool