London Bridge Rebuilding Works
Thameslink Programme
Construction Begins
Station rebuilding has been undertaken in conjunction with what has become known
as the ‘’London Bridge Quarter’’. This project involved complete redevelopment
of the site bordering the original station entrance, seeing the demolition of
two 1970s skyscrapers and the external refurbishment of the tower housing Guy’s
Hospital.
The first signs of upheaval occurred in March 2008 when scaffolding appeared
around ‘’Southwark Towers’’. This was a 24-storey skyscraper which backed onto
the terminus part of the station, having been completed in 1975 on the former
sites of the booking office and Terminus Hotel. The latter was built in 1861, but was completely
destroyed by a bombing raid in 1940. Demolition of ‘’Southwark Towers’’ was
finished in December 2008 and in February of the following year, work on ‘’The
Shard of Glass’’ got underway on the same site (the formal date of construction
work starting was given as 16th March). This colossus requires no introduction:
the plans outlined a 95-storey tower, 1016-feet high (310 metres), comprising a
steel frame clad with 11,000 individual panes of glass, all at a cost of
£450,000,000.
In October 2009, multinational construction company ‘’Skanska’’ was awarded the
contract to construct the 400-metre Borough Market Viaduct. The project was
worth £59,200,000, with preparations for construction scheduled to start in the
same month. This element of the project brought its own set of challenges, given
that the course of the new viaduct was to cut straight through the roof of the
historic Borough Market. To compensate for this, dismantling of the market’s
original cast iron framework was accommodated in the scheme; it would
subsequently be stored, refurbished, and reassembled around the new viaduct,
albeit in a slightly revised position. A number of vintage buildings also
blocked the proposed path of the new viaduct
– some
were completely removed, whilst others were only partially demolished to
accommodate the structure.
In January 2010, the next phase of site clearance began with the erection of
scaffolding around ‘’New London Bridge House’’. This was a 25-storey skyscraper,
completed in 1967, which sat opposite the station forecourt. Its site had been
earmarked for ‘’London Bridge Place’’ (also known as the ‘’Baby Shard’’), a
17-storey glass-clad office block rising up to 88-metres (289-feet) in height,
with a price tag of £200,000,000.
Piling for the viaduct was completed in September 2010, after which followed the
building of a series of paired 1.8-metre-diameter columns. These were to uphold
steel box girders supporting a prefabricated concrete deck, and the first
sections of steel were lifted upon the columns over the weekend of 9th/10th
October 2010. This initial stage of construction involved building a 128-metre
section of the viaduct west of Borough High Street and, to the east, a 50-metre
stretch. To fill the breach over the road, a 70-metre-long 1,500 tonne steel
bridge was constructed upon the western section of the viaduct. This was then
‘’slid’’ into position over Borough High Street during a road closure, enacted
from 02:00 Saturday 30th April 2011 to 05:00 on Tuesday 3rd May 2011. The main
works on the viaduct were deemed complete in summer 2012, although it had yet to be connected
at its eastern end, pending the demolition of the remaining
façade and offices of the existing station. These works had started to gather pace in
March 2011.
In April 2012, construction of a ‘’crash deck’’ began around the trainshed of
the terminal platforms, to facilitate demolition. By March 2013, most of the
trainshed had been removed, although some of the columns were still standing on
platforms 11/12 and 15/16, with the charred remains of the ornate roof brackets.
Temporary canopies and lighting had also been installed along the terminal
platforms. Although the platform numbers reached 16, there were fifteen of them –
the gap in numbering was a result of the ‘’passing loop’’ which ran beside the
line of platform 6.
The Shard was formally opened on 5th July 2012, although the structure had been
completed in the April. As part of this scheme, the London Bridge Quarter
development programme funded a new glazed concourse behind the station’s
terminal platforms and provided a replacement bus station on ‘’Railway
Approach’’. The latter opened on Monday 14th May 2012.
Over the Bank Holiday weekend of Saturday 25th May 2013 to Monday 27th May 2013,
the terminal platforms at London Bridge were closed, to enable preparations for
reconstruction. Platform Nos. 8 to 13 reopened on the following Tuesday, but
Nos. 14 to 16 remained closed for rebuilding
– from
then on, there would be no platform numbered 16 at the station.
The new platform Nos. 14 and 15 were brought back into use on Monday 31st March 2014,
which coincided with the closure of Nos. 12 and 13 for rebuilding. Due to the
location of the existing signal box, platform 15 could not be taken beyond
ten-car capacity, whilst its counterparts would be able to accommodate
twelve-vehicle trains. By this time,
£6,500,000,000 was being reported as the cost of the entire ‘’Thameslink’’
scheme.
A complete closure of the terminal platforms was enacted from 23rd August 2014
until 31st August 2014 (inclusive), resulting in no ''Southern'' or Thameslink services calling at the station during this time. This was to enable
track relaying on the terminus approaches, in addition
to further platform and canopy construction.
10th March 2012
Perched upon the viaduct is the London Bridge Panel, which was fully commissioned on 17th April 1976. The presence of the signal box prevents the extension of platform 15 beyond ten-vehicle capacity. © David Glasspool
10th March 2012
At this stage, part of the SER offices along Tooley Street was occupied by the ''Britain at War'' Museum, which recounted the Blitz of World War II. Due to impending demolition of the building, this closed in January 2013. © David Glasspool
10th March 2012
The new glazed concourse behind the terminal platforms was funded as part of the ''London Bridge Quarter'' development. At the time of this view, the 1970s structures still bordered the new concourse along the left-hand side. © David Glasspool
10th March 2012
Behind the barricade in this Cannon Street-bound view is the new bus station which, like the concourse, was funded as part of the ''London Bridge Quarter'' development. This came into use on 14th May 2012. The building taking shape on the left is the ''Baby Shard''. On the right is the framework of the 1970s façade, which was in the process of demolition. © David Glasspool
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated