Yeovil Junction
At the turn of the 20th Century, the LSWR began in earnest to make improvements
to its profitable main line to the south west, commencing in 1901 with the
rebuilding of Salisbury station. Next on the agenda was removing the bottleneck
at Yeovil Junction, which led to powers being obtained in 1906 for a major
reconstruction scheme. This commenced in the following year, at a cost of
£47,400 (about £3,737,000 at 2008 prices), and aimed to provide a layout with
eased speed limits and the facility for expresses to overtake stopping services.
The LSWR sidings south of the station were removed, to permit the construction
of a brand new island on a new alignment and the total abolition of the existing
surfaces. A second island (‘’up’’ side) was erected on a site a little to the
north of its predecessor, and earthworks were undertaken to widen the railway
embankment at its northern end. The latter resulted in the laying of an enlarged
goods yard on the ‘’up’’ side, comprising eight lengthy eastward-facing sidings,
in addition to a pair of shorter sidings serving a dock platform and cattle
pens. The earlier goods shed was incorporated into the new layout. On the
southern side of the site, the turntable and water tower remained in situ, and
connections with the Clifton Maybank branch were retained. ‘’Up’’ and ‘’down’’
island platforms measured 650-feet and 550-feet in length respectively, and both
surfaces were host to attractive single-storey red-brick offices, the latter
protected by copious canopies. The offices and canopies were of a standardised
design, and virtually identical examples had earlier appeared during the
Salisbury station reconstruction works of 1901-1902. Both platform canopies
extended to a length of 285-feet, and were supported upon a cast-iron framework
with two lines of struts. The islands were linked by a sizeable footbridge, over
100-feet in length, of lattice construction and fully enclosed. This was
positioned at the western end of the layout, and was accompanied by a barrow
crossing running between the islands. A new signal box, wholly brick-built and
with a slated hipped roof, came into use in the fork between the diverging
Salisbury and the Yeovil Town lines. At the western end of the layout, the
existing signal box of about 1875 origin was retained. This was built to a
standard LSWR design of clapboard construction with a hipped slated roof, and
could be found at virtually all stations between Yeovil and Exeter. The GWR also
retained a signal box at Clifton Maybank Junction, where their goods branch left
the Pen Mill to Weymouth line. Finally, the Station Master was provided with an
attractive detached house, of red brick construction, positioned at the top of
the station approach road, on the ‘’up’’ side of the layout. All works were
deemed complete in 1909.
On the advent of the Southern Railway in 1923, both Salisbury and Yeovil
Junction were still considered modern station rebuilds and, as a result,
infrastructure alterations were limited. Indeed, the SR’s trademark Swan Neck
lamp posts appeared on the platforms, but Yeovil Junction remained very much an
LSWR affair. The GWR withdrew from the site in July 1937, when traffic ceased to
be carried over the Clifton Maybank branch on 17th of that month. The 21-lever
signal box at Clifton Maybank Junction remained in use until 1st November of the
same year; the transfer shed at the Junction station retained a rail connection
until 1952,
and the branch became an elongated siding. In the past, the GWR had ambitions to
provide this branch with an additional Weymouth-facing connection, creating a
triangular junction, but works got no further than forming an embankment south
of the LSWR station. Goods traffic continued to be transferred between SR and
GWR systems, but this now took place at Yeovil Hendford. During World War II,
new connections were made between SR and GWR metals in the area. Crossovers were
installed to link the SR’s Yeovil Town branch with the GWR’s Pen Mill to
Weymouth line, creating a triangular junction in-between the two stations. This
became ‘’Yeovil South Junction’’, and came into use – complete with a new
austere brick-built rectangular signal box – on 13th October 1943. This was a
strategic wartime measure to permit running of Paddington to Exeter expresses by
means of the SR’s route via Yeovil Junction, in the event that the Berks & Hants
line west of Castle Cary was bombed. Finally, in 1945, the 50-foot 1-inch
turntable at Yeovil Junction was replaced by a larger Cowans Sheldon product in
1945. The latter was of 70-foot diameter and had been designed to accommodate
the large Bulleid Pacifics which were then being introduced.
We now pass into the British Railways era, and so embark on a sad story of
decline for this once busy station. Lines west of Salisbury came under
Paddington’s wing on 15th September 1962, and it was not long before a
programme of severe degrading was implemented, in favour of the Western Region’s
own main line to the south west via Castle Cary. In 1964, closure of Yeovil
Junction was proposed, and passenger traffic was to be concentrated at Sherborne,
4½ route miles to the east. Considerable local opposition killed this idea stone
dead, but rationalisation of the layout remained on the agenda. General goods
traffic at Yeovil Junction ceased on 5th April 1965, it being transferred to the
WR’s Yeovil Hendford. Singling of the route from Salisbury commenced in April
1967, beginning with that section between Wilton and Templecombe. In May of the
same year, singling between Templecombe and Chard Junction commenced. Yeovil
Junction ‘’West’’ box was abolished on 30th April 1967, and the ‘’down’’ island
platform decommissioned. Connections north of the station were also heavily
rationalised: the direct spur to Yeovil Town from the Junction station was
severed on 1st March 1967, and the ex-LSWR Yeovil Town branch between Yeovil
Junction and Yeovil South Junction was singled on 26th May 1968. Yeovil Junction
‘’East’’ box was retained and from 4th January 1970, controlled the single line
eastwards through Sherborne. Now, it was not possible to pass trains in the
station, and the ‘’down’’ platform had gone into the possession of the permanent
way department. Remarkably, the turntable was retained, in addition to the
‘’down’’ platform offices and canopy, although a notable casualty was the water
tower.
1967 track rationalisation left Yeovil Junction with just one operating through
platform face, and it was no longer possible for trains to pass each other in
the station. ‘’Down’’ trains would be held outside the station until ‘’up’’
services passed, which made maintaining the advertised timetable difficult. So
restrictive was this operating practice that track layout alterations were
enacted in 1975. Since the 1907 to 1909 rebuilding of the station, the northern
face of the ‘’up’’ island platform line never had a direct connection with the
‘’up’’ line at its western end – thus, it was essentially a bay line used by the
Yeovil Town shuttle. This was subsequently converted to a through platform loop
to allow trains to pass each within the station, and works were deemed complete
on 26th March 1975. A minor track layout upgrade was later followed by further
structural cutbacks: during 1983, the canopy of the defunct ‘’down’’ island was
dismantled, but the red brick offices retained. The Civil Mechanical &
Electrical Engineers department finally vacated the ''down'' side in 1993 and
the threat loomed of the turntable being removed. Consequently, in that year, a
meeting was held by a group interested in preserving the ''down'' side for
posterity: this stretched from as far east as the remaining track of the GWR's
Clifton Maybank branch, to as far west as the turntable. The ''South West Main
Line Steam Group'' took out a 99 year lease on the whole site (excluding the
transfer shed), which secured the long-term future of the buildings. The
''Yeovil Railway Centre'', as it became known, went from strength to strength
and on 2nd October 1999, a new double-track engine shed was opened, providing
much needed covered accommodation. A major acquisition was that of the transfer
shed: this was taken out on lease on 1st July 2002, when its departmental
function ceased.
Many thanks to Paul Gould for providing the information on the Yeovil Railway Centre.
29th November 1986
Class 33 No. 33103 is seen at the station after terminating with a 4TC unit from Salisbury. These diesels were regular performers on the Waterloo to Exeter route from 1971 onwards, when they replaced the ''Warship'' Diesel Hydraulics. The Class 33s were themselves displaced from route by the introduction of more powerful Class 50 diesels, in May 1980. © David Glasspool Collection
August 1990
Class 50 No. 50044 ''Exeter'' is seen departing the remaining island platform with a service for its namesake. The once lengthy footbridge was truncated during rationalisation in 1967, thus it now only spans the gap between the former ''up'' island and the car park, over a single track. © Mike Glasspool
August 1990
A westward view shows the departing train of colourful BR Mk 2a carriages, embarking on the single-track to Crewkerne. © Mike Glasspool
Return to the Kent Rail Homepage or alternatively, check for Updates.
Website & Copyright information - Links - Contact the Webmaster
All content is copyright © David Glasspool unless otherwise stated