London Bridge Rebuilding Works
Thameslink Programme
29th March 2013
New canopy framework had been erected around some of the still standing LB&SCR columns on platform Nos. 11 and 12. © David Glasspool
29th March 2013
A section of the ''crash deck'' still spanned the platforms at this time, marking the former position of the trainshed's eastern limit. The highest point on ''The Shard'' skyscraper dominating the background is 308 metres (1010.50 feet) in the air. © David Glasspool
29th March 2013
Redevelopment of the through station had yet to begin and was nearly two years away. Works were scheduled to start on 20th December 2014, when platform Nos. 5 to 9 would close for rebuilding. This eastward view from platform No. 3 shows the Tooley Street offices still standing on the left. © David Glasspool